Woodside Energy’s Scarborough energy project has achieved a major engineering milestone with the joining together of the topsides and hull for the Floating Production Unit (FPU).Constructed separately at two different fabrication yards
Woodside Energy’s Scarborough energy project has achieved a major engineering milestone with the joining together of the topsides and hull for the Floating Production Unit (FPU).
Constructed separately at two different fabrication yards in China, the joining of the two mega-structures is a significant step forward for the Scarborough energy project as it progresses towards first liquefied natural gas (LNG) cargo, targeted for the second half of 2026.
The floatover required precise planning and extensive collaboration by all stakeholders. Teams from Woodside, McDermott, QMW and COSCO worked closely on the fabrication of the structures and to safely bring them together.
The contract, awarded to McDermott in 2021, followed the successful delivery of front-end engineering design for the Scarborough energy project's FPU and includes engineering, procurement, construction, installation and commissioning (EPCIC) services.
McDermott is delivering design, fabrication, integration, transportation and installation of an approximately 30,000-metric-ton topside and 37,000-metric-ton hull structure, making it the largest floating production facility the company has ever designed and built, and one of the largest semi-submersible production platforms built in offshore history.
Topsides fabrication was completed at McDermott's joint venture yard, Qingdao McDermott Wuchuan (QMW), in Qingdao, China, while the hull was constructed by COSCO in its