Enshore Subsea has installed the first of two offshore export cables at Inch Cape offshore wind farm, using the CMOS Installer cable laying vessel.Operating from the Port of Blyth…
Published
Enshore Subsea has installed the first of two offshore export cables at Inch Cape offshore wind farm, using the CMOS Installer cable laying vessel.
Operating from the Port of Blyth, the vessel installed the first of two 85-kilometre export cables for the 1.1 GW offshore wind farm, being built off the east coast of Scotland.
The 220 kV, three-phase export cable was installed in three 28-kilometre sections.
Once operational, the cable will transmit power from the offshore wind farm to the project’s new onshore substation under construction at Cockenzie, East Lothian
The cable required two offshore joints which were completed using North Sea Giant and will shortly be buried in the seabed.
Manufactured by Ningbo Orient Wires & Cables (Orient Cable), the 2000 mm2 cable is among the largest AC export cables in the world. The second 85-kilometre export cable will also be installed by Enshore Subsea in